Converting on-street parking into an addtional travel lane along SW 8 Street between SW 4 Avenue and SW 2 Avenue
-
Reconstructing concrete sidewalks
-
Repaving and restriping the roadway
SAFETY
-
Installing pedestrian curb ramps, pedestrian detectors, pushbuttons and detectable warning surfaces
-
Upgrading pedestrian signalization and signage
-
Upgrading overhead signage at SW 4 Avenue entrance ramp onto SR 9A/Interstate 95
RESILIENCY
-
Installing new stormwater drainage systems between SW 21 Avenue and SW 19 Avenue
SUPPLY CHAIN
-
Installing an additional eastbound through-lane along SW 8 Street between SW 4 Avenue and SW 2 Avenue
-
Installing a dedicated left turn lane along SW 8 Street at the intersection with SW 2 Avenue
TECHNOLOGY
-
Replacing traffic signals along SW 8 Street at the intersections of SW 4 Avenue, SW 3 Avenue and SW 2 Avenue
WORKFORCE DEVELOPMENT
-
This project creates opportunities for contractors resulting in positive economic benefits for workers and the community
- 7:30 p.m. to 5:30 a.m., Monday through Thursday
- 10 p.m. to 5:30 a.m., Monday through Thursday
Access to businesses and residences will be maintained. Lane closure information is posted weekly on the department's website, www.southflroads.com.
| Start Date |
|---|
| November 2024 |
Est. Completion |
| Fall 2025 |
Construction Cost |
| $6.1 million |
Lengths and Limits |
| from east of SW 27 Avenue to east of SW 2 Avenue |
FDOT South Miami-Dade & Monroe Counties Resident Engineer |
| Dru Badri, P.E. |
FDOT Project Manager |
| Carmen E. Negron, P.E. |
FDOT Project Administrator |
| Ricardo Sargen, P.E. |
Contractor |
| H & R Paving, Inc. |
Community Outreach Specialist |
| Annabella Vizcaino Quest Corporation of America C: (786) 510-6113 |