The Florida Department of Transportation (FDOT) began a roadway project along the Palmetto Expressway in Miami-Dade County.
- Temporarily converting one southbound express lane to a non-tolled, general-purpose lane at NW 103 Street/W 49 Street to provide an additional general-purpose lane
- Extending the auxiliary lane between Okeechobee Road and NW 74 Street
- Widening the southbound bridges over NW 74 Street, Metrorail and FEC Railway
- Widening the northbound bridge over NW 103 Street/W 49 Street
- Relocating the express lane entrance at NW 154 Street to NW 103 Street/W 49 Street to allow access to the express lanes from NW 154 Street and NW 122 Street/W 68 Street
- Modifying the flyover ramp from westbound NW 103 Street/W 49 Street to southbound SR 826 along the outside non-tolled, general-purpose lane
- Widening the SR 826 bridge over NW 103 Street/W 49 Street to create a permanent, additional non-tolled, general-purpose lane
- Resurfacing the frontage roads from SR 25/US 27/Okeechobee Road to SR 932/NW 103 Street/W 49 Street and from SR 932/NW 103 Street/W 49 Street to NW 122 Street/W 68 Street
LANE CLOSURE INFORMATION
One lane Two or more lanes
- 9 p.m. to 6 a.m. 12:30 a.m. to 5 a.m. Mondays - Thursdays
- 11 p.m. to 8 a.m. 12 a.m. to 7 a.m. Fridays
- 11 p.m. to 9 a.m. 12 a.m. to 7 a.m. Saturdays
- 11 p.m. to 6 a.m. 12 a.m. to 5 a.m. Sundays
Start Date |
---|
April 2022 |
Est. Completion |
Early 2025 |
Construction Cost |
$66 million |
Lengths and Limits |
From south of NW 36 Street to north of NW 154 Street/Miami Lakes Drive |
FDOT South Miami-Dade & Monroe Counties Resident Engineer |
Dru Badri, P.E. |
FDOT Construction Project Manager |
Enmanuel “Manny” Espinal, M.S.E.M., P.E. |
CCEI Senior Project Engineer |
David C. Tinder, P.E. (FL,GA,TX,PR) BCC Engineering |
Contractor |
De Moya Group / AGI with Hardesty and Hannover |
Community Outreach Specialist |
Maria Camacho Quest Corporation
C: (305) 731-7699
|