The Florida Department of Transportation (FDOT) is scheduled to begin bridge replacement project during the week of October 8, 2024 along SR 90/SW 8 Street in Miami-Dade County.
FDOT COMPASS
FDOT is committed to ensuring the State’s infrastructure serves residents, businesses, and visitors to meet their current and future transportation needs. Benefits of this project include:
COMMUNITIES
-
Installing a pedestrian bridge over SW 8 Street and the C-4 Canal to connect communities
-
Providing pedestrian plazas with elevators and stairs at the north and south plazas
SAFETY
-
Installing a signalized pedestrian crosswalk along SW 109 Avenue, north of SW 7 Terrace
-
Upgrading pedestrian signals, signage and curb ramps
-
Closing the hisorical bridge over C-4 canal and eliminating the pedestrian crosswalks at SW 8 Street and SW 109 Avenue
RESILIENCY
- This bridge design is engineered to endure Florida's unique weather conditions.
SUPPLY CHAIN
- This project benefits the movement of people and goods in the region by separating vehicular and pedestrian traffic
TECHNOLOGY
-
Upgrading pedestrian signals and implementing signalized crosswalks with advanced traffic management systems
-
Utilizing advance sensing technology to detect pedestrian presence and adjust signal timings
WORKFORCE DEVELOPMENT
- This project creates opportunities for contractors resulting in positive economic benefits for workers and the community
PROJECT AREA MAP
LANE CLOSURE INFORMATION
Work will be done in phases to reduce the effects of construction on the community.
Lanes can be closed during the following hours:
- 10 p.m. to 5:30 a.m., Sunday through Thursday nights
- 11 p.m. to 6 a.m., Friday and Saturday nights
Roadway lane closures and detours will be established during any overhead work and as necessary to ensure safety during construction.
Travel lanes on both directions will be shifted south to create a work zone on the north side of the roadway. The number of lanes will remain the same.
- Adding a pedestrian crosswalk along SW 109 Avenue, south of SW 7 Street
- Directing pedestrians to use the historic bridge on the east side of SW 109 Avenue to cross the C-4 Canal
- Directing pedestrians to use the north-south crosswalk on the east side of SW 8 Street
Start Date |
---|
October 2024 |
Est. Completion |
Summer 2026 |
Construction Cost |
$38 Million |
Lengths and Limits |
SR 90/US 41/SW 8 St at SW 109 Ave and SW 109 Ave from SW 7 Ter to SW 6 St |
FDOT South Miami-Dade Resident Engineer |
Enmanuel “Manny” Espinal, M.S.E.M., P.E. |
Consultant Construction Engineering and Inspection (CCEI) Project Engineer |
Arturo J. Perez, P.E., P.S.M Pinnacle Consulting Enterprises, Inc. |
Contractor |
De Moya Highway Infrastructure, LLC. |
Community Outreach Specialist |
Jeff Baquedano Quest Corporation of America C: (786) 510-6113 O: (305) 640-7462 |