Welcome
 
 
The Florida Department of Transportation (FDOT) began a roadway project on November 4, 2024 along SR 5/US 1/ Biscayne Boulevard from north of NE 105 Street to SR 922/NE 123 Street and along SR 922/NE 123 Street from NE 16 Avenue to east of N Bayshore Drive in Miami-Dade County.
 

 

FDOT COMPASS

 

COMMUNITY

  • Constructing an additional designated westbound left turn lane on SR 922/NE 123 Street to access southbound SR 5/Biscayne Boulevard
    • Extending the eastbound dual left turn lanes to improve the flow of traffic at the intersection

 

SAFETY

  • Upgrading vehicular and pedestrian signals, signage and pavement markings

 


 

RESILIENCY

  • Upgrading drainage pipes and the stormwater pump system to improve capacity

 


 

SUPPLY CHAIN

  • Repaving and restriping to preserve the service life of the road

 


 

TECHNOLOGY

  • Installing pavement traffic detectors to identify vehicles approaching the traffic lights

 


 

WORKFORCE DEVELOPMENT

  • This project creates opportunities for contractors, which results in positive economic benefits for the workers and the community

LANE CLOSURE INFORMATION

Work will be done in phases to reduce the effects of construction on the community. Lanes can be closed during the following hours:

  • SR 5/US 1/Biscayne Boulevard single lane closures will occur during non-peak hours or non-event days. Non-peak hours are:
  • 10 p.m. to 6 a.m., Sunday through Thursday
  • 9 a.m. to 4 p.m., weekdays and weekends
  • SR 922/NE 123 Street and side street single lane closures will occur during non-peak hours or on non-event days. Non-peak hours are:
  • 10 p.m. to 6 a.m., Sunday through Thursday
  • 9 a.m. to 4 p.m., weekdays and weekends
Project At-A-Glance
 
map
Start Date
November 2024

Est. Completion
Fall 2025

Construction Cost
$8.8 million

Lengths and Limits
SR 5/US 1/ Biscayne Bouelvard from north of NE 105 Street to SR 922/NE 123 Street and along SR 922/NE 123 Street from NE 16 Avenue to east of N Bayshore Drive

FDOT North Miami-Dade Resident Engineer
Ivan Hay, P.E.

FDOT North Miami-Dade Assistant Resident Engineer
John M. Garzia, P.E.

FDOT Project Manager
John M. Garzia, P.E.

Project Administrator
Franche Perdomo

Contractor
OHLA USA, INC.

Community Outreach Specialist
Aliyah Gomez
Holt Communications, Inc.

O: (786) 837-4884

C: (786) 774-9714
Aliyah.Gomez@dot.state.fl.us

×