Welcome
The Florida Department of Transportation (FDOT) began a roadway project on April 7, 2025 along SR 932/NW 103 Street/W49 Street from west of W 24 Avenue/NW 82 Avenue to east of W 6 Avenue in Miami-Dade County.
FDOT COMPASS
COMMUNITY
- Removing abandoned driveways within the project limits.
- Upgrading vehicular and pedestrian signals, signage, and crosswalks.
.png)
SAFETY
- Reconstructing damaged sidewalks and driveways
.png)
RESILIENCY
- Repaving and restriping to preserve the service life of the road
.png)
SUPPLY CHAIN
- Replacing and upgrading pedestrian curb ramps
.png)
TECHNOLOGY
- Installing new countdown pedestrian signals and push button poles
.png)
WORKFORCE DEVELOPMENT
- This project creates opportunities for contractors, which results in positive economic benefits for the wokers and the community
LANE CLOSURE INFORMATION
Travel lanes and sidewalks will be closed during non-peak hours on non-event days. Non-peak hours are:
- 9 p.m. to 5:30 a.m., Sunday through Thursday nights
- 11 p.m. to 7 a.m., Friday and Saturday nights
No work or lane closures are allowed during school speed zone hours.
Project At-A-Glance
| Start Date |
|---|
| April 2025 |
Est. Completion |
| Spring 2026 |
Construction Cost |
| $8.3 million |
Lengths and Limits |
| From west of W 24 Avenue/NW 82 Avenue to east of W 6 Avenue |
North Miami-Dade Resident Engineer |
| Ivan Hay, P.E. |
North Miami-Dade Assistant Resident Engineer |
| John M. Garzia, P.E. |
FDOT Project Manager |
| Colin W. Johnson, P.E. |
Senior CEI |
| Brandon Bagett, P.E. Castillo Engineering, Inc. |
CEI |
| Andres Diaz, P.E. Castillo Engineering, Inc. |
Contractor |
| BACCALLAO CONSTRUCTION, INC. |
Community Outreach Specialist |
| Annabella Vizcaino Quest Corporation of America C: (786) 510-6113 |