The Florida Department of Transportation (FDOT) is scheduled to begin a ramp rehabilitation project the week of June 4, 2025 along SR 970/Downtown Distributor Ramps in Miami-Dade County.
FDOT COMPASS
FDOT is committed to ensuring the State’s infrastructure serves residents, businesses, and visitors to meet their current and future transportation needs. Benefits of this project include:
COMMUNITIES
-
Enhancing mobility and connectivity by improving bridge conditions, helping maintain reliable access for residents and commuters
SAFETY
-
Replacing traffic railing and barriers for roadside protection for motorists
-
Performing concrete repairs to improve surface conditions
-
Replacing bearing pads to stabilize bridge components
-
Upgrading bridge expansion joints
RESILIENCY
-
Reparing damaged concrete on the bridge deck Performing concrete repairs to improve surface conditions
-
Rehabilitating reinforcing and structural steel on the bridge
-
Protecting the bridge's surface with a coating that helps prevent moisture damage
SUPPLY CHAIN
-
Repaving and restriping the roadway
-
Improving structural reliability of the bridge facilities facilitates the movement of goods, serving residents and contributing to the supply chain
TECHNOLOGY
-
Using durable materials and modern treatment techniques to enhance infrastructure performance and longevity
WORKFORCE DEVELOPMENT
- This project creates opportunities for contractors resulting in positive economic benefits for workers and the community
Project Area Map
LANE CLOSURE INFORMATION
Work will be done in phases to reduce the effects of construction on the community.
Lanes can be closed during the following hours:
Single-lane closures may be in place:
- 9 p.m. to 7 a.m., Sunday through Thursday nights
Full ramp closures will be in place for certain work activities:
- 10 p.m. to 6 a.m., Sunday through Thursday nights
- 8 p.m. to 6 a.m., Sunday through Thursday nights
Access to businesses and residences will be maintained. Pedestrian and vehicular detours will be established with clear signage. Lane closure information is posted weekly on the department's website, www.southflroads.com.
Start Date |
---|
June 2025 |
Est. Completion |
Spring 2026 |
Construction Cost |
$2.3 million |
Lengths and Limits |
From SR 5/US 1 to SR 9A/I-95 northbound |
FDOT North Miami-Dade & Monroe Counties Resident Engineer |
Ivan Hay, P.E. |
FDOT Project Manager |
Colin Johnson, P.E. |
Consultant Construction Engineering and Inspection (CCEI) Project Engineer |
Sergio Gonzalez, P.E. |
Contractor |
Seacoast Incorporated |
Community Outreach Specialist |
Jeff Baquedano Quest Corporation of America C: (786) 510-6113 O: (305) 640-7462 |