The Florida Department of Transportation (FDOT) will begin a pedestrian project on August 21, 2025 along A1A/Harding Avenue between 87 Street and 87 Terrace and 90 Street SR A1A/Collins Avenue at 89 Street in Miami-Dade County

FDOT COMPASS

 

COMMUNITY

  • Constructing pedestrian ramps at signalized crossings
  • Constructing a mid-block crossing at Harding Avenue at 89 Street and 90 Street and Collins Avenue at 89 Street

 

SAFETY

  • Installing a traffic signal at Harding Avenue at 89 Street and 90 Street and Collins Avenue at 89 Street
  • Installing Rectangular Rapid Flashing Beacons (RRFB) at Harding Avenue between 87 Street and 87 Terrace
  • Relocating the bus stop shelter between 87 Street and 87 Terrace further north

 

RESILIENCY

  • Widening the sidewalk on the west side of Harding Avenue between 87 Street and 87 Terrace

  • Repaving and restriping the intersection


 

TECHNOLOGY

  • Upgrading existing light poles with light-emitting diodes (LED)

 


 

WORKFORCE DEVELOPMENT

  • This project creates opportunities for contractors, which results in positive economic benefits for the workers and the community

LANE CLOSURE INFORMATION

Work will be done in phases to reduce the effects of construction on the community. Lane closures shall occur during non-peak hours on non-event days/weekends. 
 
Single lane closures along SR A1A/Harding Avenue may occur:
  • 10 a.m. to 4 p.m., Monday - Friday
     
     
  • 9 p.m. to 7 a.m., Monday - Thursday

 

Single closures along SR A1A/Collins Avenue may occur:
  • 9 a.m. to 4 p.m., Monday - Friday
  • 9 p.m. to 7 a.m., Monday - Thursday
Dual lane closures along SR A1A/Harding Avenue or SR A1A/Collins Avenue may only occur during nighttime work hours.
 

 


 

Project At-A-Glance
 
map
Start Date
August 2025

Est. Completion
Spring 2026

Construction Cost
$1.7 million

Lengths and Limits
State Road (SR) A1A/Harding Avenue between 87 Street and 87 Terrace and 90 Street SR A1A/Collins Avenue at 89 Street

FDOT North Miami-Dade Resident Engineer
Ivan Hay, P.E.

FDOT Construction Project Manager
Colin W. Johnson, P.E.

FDOT Project Administrator
Franche Perdomo

Contractor
Florida Signal and Lighting Contractors, Inc.

Senior Community Outreach Specialist
Melissa J. Rodriguez

HML Public Outreach, LLC
1 (305) 570-8076
Melissa.Rodriguez@dot.state.fl.us