- Project Resources
- Documents and Publications
- Contact Us
- Lane Closures

Welcome
The Florida Department of Transportation (FDOT) began various intersection projects along State Road (SR) A1A/Collins Avenue on November 15, 2021 in Miami-Dade County.
WORK TO BE PERFORMED:
At 10, 11, 14, and 74 Street
- Replacing traffic signal mast arms
- Replacing pedestrian signal poles
- Restoring pedestrian sidewalks, curb ramps, and curb and gutters
- Repaving and restriping at the intersections of 11 Street and 14 Street
LANE CLOSURE INFORMATION:
Travel lanes and sidewalks will be closed only during non-peak hours on non-event days. Non-peak hours are:
- 9 a.m. to 3:30 p.m., weekdays and weekends
- 8 p.m. to 8 a.m., Sunday through Thursday nights
Project At-A-Glance
Start Date |
---|
November 2021 |
Est. Completion |
Spring 2024 |
Construction Cost |
$308,542 |
Lengths and Limits |
At 10, 11, 14 and 74 Street |
FDOT North Miami-Dade Resident Engineer |
Ivan Hay, P.E. |
FDOT Project Manager |
John Garzia, P.E. |
FDOT/CEI Project Administrator |
Andres Diaz, P.E. |
Contractor |
AGC Electrical, Inc. |
Community Outreach Specialist |
Christian Gonzalez
(786) 837-4884 |