The dedicated right-turn lane, along NW South River Dr, to access the southbound SR 826/Palmetto Expressway on-ramp has been removed. Motorists will still be able to make right turn to access the on-ramp from the remaining travel lane. This removal will allow the crew to perform bridge demolition and widening.
-
General Lane Closures
Closures may take place during the following hours:
- 9 a.m. to 3:30 p.m. weekdays and weekends.
- 9 p.m. to 5:30 a.m. on weekdays.
- 11 p.m. to 7:30 a.m. on weekends.
-
Various travel lane shifts have taken place along S.R. 25/U.S. 27/Okeechobee Road to allow for the expansion of the work zone. The dates and locations are as follows:
- Westbound lanes along S.R. 25/U.S. 27/Okeechobee Road from S.R. 826/Palmetto Expressway to east of W. 18 Avenue will be shifted to the north.
- Eastbound lanes along S.R. 25/U.S. 27/Okeechobee Road from east of W. 18 Avenue to S.R. 826/Palmetto Expressway will be shifted to the north.
- Ramp from Okeechobee Road to northbound S.R. 826/Palmetto Expressway will be shifted to the north.
- Exit lanes along the northbound S.R. 826/Palmetto Expressway off-ramp will be reduced from two to one lane. Lanes along NW South River Drive will remain the same.
-
Various lane reductions and traffic shifts have taken place as part of the S.R. 25/U.S. 27/Okeechobee Road Reconstruction Project. These shifts are necessary to allow crews to perform drainage and sidewalk improvements and expand the construction work zone. The new traffic patterns will be in place until Fall 2026.
The dates and locations are as follows:
- Right turn lane from northbound NW 79 Avenue to eastbound S.R. 25/U.S. 27/Okeechobee Road will be temporarily removed.
- Travel lanes along W 18 Avenue between S.R. 25/U.S. 27/Okeechobee and W 35 Street will be shifted to the east, and lanes will be reduced from two to one lane in each direction.
-
Travel lanes in both directions on the NW 79 Ave bridge between S.R. 25/U.S. 27/Okeechobee Rd and NW South River Dr have been shifted to the east. This shift will allow crews to continue reconstruction and widening of the bridge.
Large trucks will not be able to turn right from eastbound S.R. 25/U.S. 27/Okeechobee Rd onto southbound NW 79 Ave. Trucks will need to use the following intersection at southbound S.R. 826/Palmetto Expy on-ramp to access NW 79 Ave. A No Turn on Red restriction will also be in place at this intersection.
-
Beginning Monday, November 16, 2026, the traffic pattern along NW South River Dr
between NW 91 Terr and NW 79 Ave will shift as crews continue reconstruction of the
roadway. The westbound travel lane will shift to the north side of the roadway, while the
eastbound travel lane will remain closed. The eastbound lane closure will remain in place
through Summer 2027
Access to adjacent businesses and neighborhoods will be maintained at all times through
NW 91 Terr and NW 90 St.