Project Summary

 
The Florida Department of Transportation (FDOT) began a safety improvement project on August 26, 2026, along the State Road (S.R.) 826/Palmetto Expressway southbound off-ramp to eastbound S.R. 90/SW 8 Street, in Miami-Dade County.
 

Project Scope of Work

  • Resurfacing the ramp with high-friction asphalt to improve vehicle control 
  • Installing dynamic curve warning signage that activates when drivers approach 
  • Adding new pavement markings along the ramp 
  • Restriping the existing pedestrian crosswalk 
  • Adding new advanced warning signage on the ramp’s entrance 
  • Installing new guardrail and traffic delineators 

Lane Closure Information

Work will be done in phases to reduce the effects of construction on the community. Lanes can be closed during the following hours: 

  • 10 p.m. to 8 a.m., Sunday through Thursday 
  • 11 p.m. to 7 a.m., Friday and Saturday 

Access to businesses and residences will be maintained at all times. Pedestrian and vehicular detours will be established with clear signage. Weekly lane closure updates are posted at www.SouthFLRoads.com. 


Detour Information

There will be a closure of the S.R. 826/Palmetto Expressway southbound off-ramp to eastbound S.R. 90/SW 8 Street as crews work on improvements. The closure hours are as follows:

  • 10 p.m. to 8 a.m., Sunday through Thursday 
  • 11 p.m. to 7 a.m., Friday and Saturday

A detour will be in place between these hours. Traffic will be directed through the following route:

  • Exit at the S.R. 826/Palmetto Expressway southbound off-ramp to westbound S.R. 90/SW 8 Street
  • Continue westbound and U-turn at S.R. 973/SW 87 Avenue
  • Continue eastbound on S.R. 90/SW 8 Street and return to original route

 This closure and detour will be in place on an as-needed basis during the allowable hours for off-ramp improvements.

 

Current Status / Upcoming Activities

Construction is currently in progress. Below are the activities planned for the weeks of November 9 and November 16.

 

Week of November 9

  • Widening the ramp's shoulder
  • Constructing concrete spillway
  • Installing signage

 

Week of November 16

  • Widening the ramp's shoulder
  • Constructing concrete spillway
  • Installing signage