About

The Florida Department of Transportation (FDOT) began a roadway project the week of January 5, 2026, along State Road (S.R.) 976/Bird Road/SW 40 St from east of Laguna Street to west of SW 38 Avenue and S.R. 953/S.R. 952/LeJeune Road/SW 42 Avenue in Miami-Dade County and the City of Coral Gables.


FDOT COMPASS

FDOT is committed to ensuring the State’s infrastructure serves residents, businesses, and visitors to meet their current and future transportation needs. Benefits of this project include:

Communities

COMMUNITIES

  • Reconstructing concrete sidewalks and curb and gutters

  • Implementing green colored pavement markings and signage at trail crossings


Safety

SAFETY

  • Upgrading pedestrian signage

  • New signalized pedestrian midblock crossing

  • Installing Ground Mounted "No Turn on Red Signs"


Resiliency

RESILIENCY

  • Installing drainage improvements

 


Supply

SUPPLY CHAIN

  • Repaving and restriping the roadway

 


Technology

TECHNOLOGY

  • Replacing various traffic signals and pedestrian signals

  • Installing traffic video detection systems on existing traffic signals and new traffic monitoring site


Workforce

WORKFORCE DEVELOPMENT

  • This project generates opportunities for local contractors and suppliers, providing economic benefits for workers and the surrounding community

 


LANE CLOSURE INFORMATION

Work will be done in phases to reduce the effects of construction on the community.

Lanes can be closed during the following hours:

For construction along Bird Road requiring lane closures:
• Eastbound: 8:30 p.m. to 6:30 a.m., Weekdays
• Westbound: 10 p.m. to 8 a.m., Weekdays


For construction along LeJeune requiring lane closures:
• 9 a.m. to 3:30 p.m., Weekdays and Weekends
• 10 p.m. to 6:30 a.m., Sunday through Thursday nights
• 11 p.m. to 8 a.m., Friday and Saturday nights

Access to businesses and residences will be maintained. Pedestrian and vehicular detours will be established with clear signage. Lane closure information is posted weekly on the department's website, www.southflroads.com.
 

PROJECT LIMIT MAPS

 

Current Status / Upcoming Activities

Construction is currently in progress. The follow activities are scheduled for the weeks of June 22 and June 29:

Week of June 22

Construction along Bird Road

  • Traffic signal cabinet installation

Construction along LeJeune Road

  • Drainage work along Greco Avenue
  • Concrete work along Altara Avenue
  • Concrete work along Alminar Avenue
  • Concrete work along Ponce de Leon Boulevard

Week of June 29

Construction along Bird Road

  • Traffic signal cabinet installation

Construction along LeJeune Road

  • Concrete work along Ponce de Leon Boulevard
  • Concrete work along Greco Avenue