The Florida Department of Transportation (FDOT) is developing the design for a roadway project along State Road (SR) 953/LeJeune Road/SW-NW 42 Avenue from SW 8 Street to NW 11 Street, in Miami-Dade County.
WORK TO BE PERFORMED:
- Providing a southbound left-turn and U-turn movements at SW 5 Terrace
- Closing median openings at SW 4 Street and SW 2 Terrace
- Adding a northbound directional median opening at SW 2 Street
- Closing two abandoned driveways at NW 4 Street
- Repaving and restriping the road
- Improving stormwater drainage system
- Replacing traffic signal at the NE corner of Flagler Street
- Upgrading signs and pavement markings
- Replacing all pedestrian push buttons
- Enhancing traffic signals
- Updating lighting
- Relocating palm trees
MAINTENANCE OF TRAFFIC
During construction, temporary lane closures during non-peak hours and detours may affect traffic. Access to adjacent businesses and residences will be maintained.
Public Meeting:
FDOT will host a Hybrid Public Meeting for those interested in learning more about this design project.
Time and Date: Tuesday, September 26, 2023 starting at 6 p.m.
Location:
In-Person Meeting:
Miami-Dade College Eduardo J Padron Campus, Room 201
627 SW 27 Avenue
Miami, FL 33135
Virtual Meeting:
Visit the link to attend: https://attendee.gotowebinar.com/register/3456502152229449312
Participants can also call in by dialing +1 (415) 655-0060; Access code: 706-357-316
Construction Start Date |
---|
August 2025 |
Construction Cost |
$3.2 million |
Lengths and Limits |
SR 953/LeJeune Road/SW-NW 42 Avenue from SW 8 Street to NW 11 Street |
FDOT Project Manager |
Alejandro Jaureguy, P.E. |
FDOT Project Manager |
Ramon Tesone, P.E. Alvarez Engineering |
Community Outreach Specialist |
Rodolfo Roman Infinite Source Communications Group O: 305-470-5477 C: 786-519-7160 |