The installation of the landscape materials was completed.
This project is currently in the establishment period.
The Florida Department of Transportation (FDOT) started a landscape project along SW 312 Street/Campbell Drive on the week of February 14, 2022 in Miami-Dade County.
The installation of trees is expected to take several months before the project moves into the establishment phase.
WORK TO BE PERFORMED
- Installing landscape within the new median
LANE CLOSURE INFORMATION
Travel lanes shall be closed only during nonpeak hours on nonevent days. Nonpeak hours are:
- 10 p.m. to 5 a.m., weekdays and weekends
Start Date |
---|
February 2022 |
Est. Completion |
Spring 2024 |
Construction Cost |
$283,092 |
Lengths and Limits |
From SR 997/Krome Avenue to SR 5/US 1 |
FDOT South Miami-Dade & Monroe Counties Resident Engineer |
Dru Badri, P.E. |
FDOT Construction Project Manager |
George Hoffman, P.E. |
Contractor |
Blue Native of the Florida Keys, Inc. |