The Florida Department of Transportation (FDOT) began a roadway project along State Road (SR) 953/LeJeune Road from NW 79 Street/E 25 Street to NW 103 Street/E 49 Street in Miami-Dade County. Click here to sign up for construction alerts.

WORK TO BE PERFORMED

  • Installing traffic signal mast arms at E 42 Street and E 41 Street
  • Reconstructing the mid-block crosswalk near Flamingo Elementary
  • Reconstructing traffic medians between E 40 Street and E 44 Street
  • Reconstructing concrete sidewalks, curb ramps, and curb and gutters
  • Upgrading vehicular and pedestrian signage and signalization features
  • Installing and/or replacing light poles with new Light-emitting Diodes (LED)
  • Enhancing drainage structures
  • Removing abandoned driveways
  • Repaving and restriping the roadway

LANE CLOSURE INFORMATION
Travel lanes and sidewalks will be closed during non-peak hours on non-event days. Non-peak hours are:

  • 9 a.m. to 3:30 p.m., weekdays and weekends
  • 9 p.m. to 6 a.m., Sunday through Thursday nights
  • 11 p.m. to 7:30 a.m., Friday and Saturday nights

DETOUR INFORMATION
Vehicular and pedestrian detours will be established at times as needed. Specific detour information will be provided before the corresponding construction activity is scheduled.

Project At-A-Glance
 
map
Start Date
November 2023

Est. Completion
Fall 2024

Construction Cost
$3.3 Million

Lengths and Limits
From NW 79 Street/E 25 Street to NW 103 Street/E 49 Street

FDOT North Miami-Dade Resident Engineer
Ivan Hay, P.E

FDOT Project Manager
Galina Belash

Contractor
H&R Paving, Inc.

Community Outreach Specialist
Christian Gonzalez

(786) 837-4884
ChristianS.Gonzalez@dot.state.fl.us