Project Summary
The Florida Department of Transportation (FDOT) is scheduled to begin a roadway project the week of May 20, 2024 along SR 25/NW 36 Street in Miami-Dade County.
WORK TO BE PERFORMED
- Installing 10 new drainage structures
- Upgrading four drainage structures
- Installing over 1,000 feet of new stormwater drainage
- Repaving and restriping the roadway within the project limits
LANE CLOSURE INFORMATION
Travel lanes and sidewalks will be closed during non-peak hours on non-event days. Non-peak hours are:
- 9 p.m. to 5:30 a.m., Sunday through Thursday
- 9 a.m. to 3:30 p.m., Weekdays and Weekends
DETOUR INFORMATION
Pedestrian and vehicular detours will be established at times and may exceed past the non-peak lane closures hours. Specific detour information will be provided before the corresponding construction activity is scheduled.
Start Date |
---|
May 2024 |
Est. Completion |
Late 2024 |
Construction Cost |
$1.4 million |
Lengths and Limits |
SR 25/NW 36 Street from NW 27 Avenue to NW 22 Avenue |
FDOT North Dade Resident Engineer |
Ivan Hay, P.E. |
FDOT North Dade Assistant Resident Engineer |
John M. Garzia, P.E. |
FDOT Project Manager |
Colin W. Johnson, P.E. |
Consultant Construction Engineering and Inspection (CCEI) Project Administrator |
Bernnon Artola Ally Engineering Services, Inc. |
Contractor |
Horizon Contractors, Inc. |
Community Outreach Specialist |
Miranda Brito Holt Communications
O: (786) 837-4884
C: (786) 774-9714
|