Procurement Schedule





Adjusted Score Design Build Procurement Schedule I75 / Palmetto Express Lanes (FM 432687-1, 432687-2 and 430795-1)


Duration between events Cumulative Days Date Event




Tuesday, January 08, 2013 I-75/Palmetto Express Lanes Project Industry Workshop: Miramar Cultural Center ArtsPark located at 2400 Civic Center Place in Miramar, Florida 33025



0 Tuesday, February 26, 2013 Submit Planned Advertisement to Carla Perry and Alan Autry for consistency review


7 7 Tuesday, March 05, 2013 Planned Advertisement (Inclusion of Draft RFP w/o attachments is encouraged)


10 17 Friday, March 15, 2013 Advertisement (On a Monday or Tuesday. Include Draft RFP w/o attachments)


21 38 Friday, April 05, 2013 Expanded Letters of Interest for Phase I of the procurement process due in District Office by [5:00 pm] local time


14 52 Friday, April 19, 2013 Proposal Evaluators submit Expanded Letter of Interest Scores to Contracting Unit [5:00 pm] local time


3 55 Monday, April 22, 2013 Public Meeting of Selection Committee to review and confirm Expanded Letter of Interest scores [9:00 am] local time


0 55 Monday, April 22, 2013 Notification to Responsive Design-Build Firms of the Expanded Letter of Interest scores [5:00 pm] local time (Design Build Firms are also provided their individual scores on this date)


2 57 Wednesday, April 24, 2013 Deadline for all responsive Design-Build Firms to affirmatively declare intent to continue to Phase II of the procurement process [5:00 pm] local time


0 57 Wednesday, April 24, 2013 Shortlist Posting [5:00 pm] local time


1 58 Thursday, April 25, 2013 Final RFP provided to Design-Build firms providing affirmative Declaration of Intent to continue to Phase II of the procurement process


22 80 Friday, May 17, 2013 Deadline for submission of written questions prior to the pre-proposal meeting. D6.designbuild@dot.state.fl.us 5:00 pm local time


7 87 Friday, May 24, 2013 Mandatory pre-proposal meeting District Office at 9:00 am local time at Florida Department of Transportation, District Six Main Building Auditorium: 1000 NW 111 Avenue Miami Florida 33172 All impacted Utility Agency / Owners are to be invited to the mandatory Pre-proposal meeting.


25 112 Tuesday, June 18, 2013 Alternative Technical Concept Meeting No. 1


14 126 Tuesday, July 02, 2013 Alternative Technical Concept Meeting No. 2 (optional)


7 133 Tuesday, July 09, 2013 Deadline for Design-Build Firms to submit Alternative Technical Concept Proposals and for the submission of Design Exceptions or Variances [5:00 pm] local time.
.+14
13 146 Monday, July 22, 2013 DDE completes review of ATCs and notifies Design-Build Firms


16 162 Wednesday, August 07, 2013 Deadline for Design-Build Firms to submit questions prior to the submittal of Technical Proposal. All questions shall be submitted to the Pre-Bid Q&A webiste


7 169 Wednesday, August 14, 2013 Deadline for the Department to post responses to the Pre-Bid Q&A website for questions submitted by the design Build Firmsprior to Submittal of the Technical Proposal.


26 195 Monday, September 09, 2013 Technical Proposals due in District Office by [5:00 pm] local time


7 202 Monday, September 16, 2013 Thirty-minute "Page Turn" of Design-Build Firm's Technical Proposal. Times will be assigned during Pre-Proposal Meeting


21 223 Monday, October 07, 2013 Question and Answer Session. Times will be assigned during the pre-proposal meeting. One hour will be allotted for questions and responses.


7 230 Monday, October 14, 2013 Deadline for Design-Build Firms to submittal of Written Clarification letter following Question and Answer Session [5:00 pm] local time


4 234 Friday, October 18, 2013 Deadline for Design-Build Firms to submit questions prior submittal of Price Proposal


7 241 Friday, October 25, 2013 Deadline for Department to submit responses prior submittal of Price Proposal


14 255 Friday, November 08, 2013 Price Proposals due in District Office by [9:00 pm] local time.


0 255 Friday, November 08, 2013 Public Meeting announcing of Technical Scores and opening of Price Proposals


5 260 Wednesday, November 13, 2013 Public Meeting of Selection Committee to determine intended Award


0 260 Wednesday, November 13, 2013 Final selection posting


7 267 Wednesday, November 20, 2013 FHWA Concurrence to Award


7 274 Wednesday, November 27, 2013 Anticipated Award Date


7 281 Wednesday, December 04, 2013 FDOT executes contract



9.4 Months