General Lane Closures
Closures may take place Monday through Saturday during the following hours:- 9 a.m. to 3:30 p.m. weekdays and weekends
- 9 p.m. to 5:30 a.m. on weekdays.
- 11 p.m. to 7:30 a.m. on weekends.
-
The dedicated right-turn lane, along NW South River Dr, to access the southbound SR 826/Palmetto Expressway on-ramp has been removed. Motorists will still be able to make right turn to access the on-ramp from the remaining travel lane. This removal will allow the crew to perform bridge demolition and widening.
-
Travel lanes along Frontage Road from NW 95 Street to NW 77 Avenue have been shifted south onto temporary pavement. This shift will be in place for approximately six months to allow for the reconstruction of Frontage Road. Access to businesses will be maintained at all times.
-
One northbound thru lane and one right-turn lane on NW South River Drive at the northbound S.R. 826/Palmetto Expressway off-ramp have been removed.
Lanes are reduced to one lane in each direction for approximately eight months while bridge reconstruction work is completed.
-
Travel lanes in both directions along Frontage Road between NW 79 Avenue and NW 77 Avenue will be closed from 11 p.m. on Friday, April 3, through Monday, April 6, 2026, for reconstruction. Access to driveways and businesses will be maintained at all times.