The Florida Department of Transportation (FDOT) is developing the design for a roadway project along SR 5/US 1/S Dixie Highway from SW 100 Street to SW 88 Street, in Miami-Dade County.
WORK TO BE PERFORMED:
- Repaving and restriping theroadway
- Adjusting manholes
- Upgrading all pedestrian signals, signs and curb ramps
- Trimming landscape
- Upgrading signage and pavement markings with special emphasis crosswalk
MAINTENANCE OF TRAFFIC
During construction, temporary lane closures and detours will affect traffic. Pedestrian detours will be established with clear signage. Access to adjacent businesses and neighborhoods will be maintained.
PUBLIC INVOLVEMENT:
In-Person Public Meeting will be held at:
A meeting was held at Coral Pine Park, Tuesday, March 15, 2022. To watch the meeting visit the link: https://register.gotowebinar.com/register/2810525863742504972.
Construction Start Date |
---|
November 2024 |
Construction Cost |
$3 million |
Lengths and Limits |
SR 5/US 1/S Dixie Hwy from SW 100 Street to SW 88 Street |
FDOT Project Manager |
Carmen Bermudez P.E. |
Consultant Design Project Engineer |
Michel Rodriguez, P.E. AES Engineering |
Community Outreach Specialist |
Rodolfo Roman Infinite Source Communications Group O: 305-470-5477 C:786-519-7160 |