Welcome
 

The Florida Department of Transportation (FDOT) is developing the design for an intersection project at SR 932/NW 103 Street and NW 32 Avenue, in Miami-Dade County.  

WORK TO BE PERFORMED: 

  • Repaving and restriping the intersection
  • Widening the median on the eastbound and westbound approaches
  • Providing an eastbound right turn lane
  • Widening the eastbound and westbound outside lanes
  • Relocating existing drainage structures
  • Reconstructing damaged and uneven sidewalk
  • Upgrading all traffic signs, crosswalks and pavement markings
  • Replacing traffic signals
  • Trimming landscaping
  • Relocating plants

MAINTENANCE OF TRAFFIC: 

During construction, temporary lane closures and detours will affect traffic. Pedestrian detours will be established with clear signage. Access to adjacent businesses and neighborhoods will be maintained.

Project At-A-Glance
 
map
Construction Start Date
August 2025

Construction Cost
$1.3 million

Lengths and Limits
State Road (SR) 932/NW 103 Street at NW 32 Avenue

FDOT Project Manager
Carmen Bermudez, P.E.


Consultant Design Project Engineer
Carlos Perez, P.E.,

CH Perez


Community Outreach Specialist
Rodolfo Roman

Infinite Source Communications

O: (305) 470-5477

Rodolfo.Roman@dot.state.fl.us