THIS PROJECT WAS COMPLETED IN MARCH 2023.
 

The Florida Department of Transportation (FDOT) began a bridge project along State Road (SR) 5/US 1/Overseas Highway on January 3, 2022 in Monroe County.

WORK TO BE PERFORMED:

  • Repairing concrete elements under the bridge
  • Sealing the bridge deck
  • Installing additional protection for foundation footers

LANE CLOSURE INFORMATION:
Travel lanes and sidewalks shall be closed only during non-peak hours on non-event days. Non-peak hours are:

  • 9:30 p.m. to 5 a.m., Monday through Thursday nights
Project At-A-Glance
 
map
Start Date
January 2022

Est. Completion
Spring 2023

Construction Cost
$760,000

Lengths and Limits
Over the Lignumvitae Channel (MM 77.5 to MM 77.7)

FDOT Assistant District Construction Engineer
Andres Berisiartu, P.E.

Construction Consulting Engineering and Inspection (CCEI) Project Manager
Anthony Sabbag
HDR, Inc.

Construction Consulting Engineering and Inspection (CCEI) Senior Project Engineer
Hector Rodriguez, M.S., P.E.
H.Rodriguez Consulting Engineering Inc.

Contractor
Freyssinet, Inc.

Community Outreach Specialist
Paulette Summers
Media Relations Group, LLC
O: (305) 254-8598