THIS PROJECT WAS COMPLETED IN MARCH 2023.
The Florida Department of Transportation (FDOT) began a bridge project along State Road (SR) 5/US 1/Overseas Highway on January 3, 2022 in Monroe County.
WORK TO BE PERFORMED:
- Repairing concrete elements under the bridge
- Sealing the bridge deck
- Installing additional protection for foundation footers
LANE CLOSURE INFORMATION:
Travel lanes and sidewalks shall be closed only during non-peak hours on non-event days. Non-peak hours are:
- 9:30 p.m. to 5 a.m., Monday through Thursday nights
Project At-A-Glance
Start Date |
---|
January 2022 |
Est. Completion |
Spring 2023 |
Construction Cost |
$760,000 |
Lengths and Limits |
Over the Lignumvitae Channel (MM 77.5 to MM 77.7) |
FDOT Assistant District Construction Engineer |
Andres Berisiartu, P.E. |
Construction Consulting Engineering and Inspection (CCEI) Project Manager |
Anthony Sabbag HDR, Inc. |
Construction Consulting Engineering and Inspection (CCEI) Senior Project Engineer |
Hector Rodriguez, M.S., P.E. H.Rodriguez Consulting Engineering Inc. |
Contractor |
Freyssinet, Inc. |
Community Outreach Specialist |
Paulette Summers Media Relations Group, LLC
O: (305) 254-8598
C: (786) 510-3921
|