The Florida Department of Transportation (FDOT) began a pedestrian and bicycle safety project along State Road (SR) 112/Arthur Godfrey Road/W 41 Street on June 7, 2021 in Miami-Dade County.

WORK TO BE PERFORMED

  • Improving signalization and lighting throughout project limits
  • Improving existing drainage structures throughout project limits
  • Installing ADA compliant sidewalks and pedestrian curb ramps
  • Constructing high emphasis pedestrian crosswalk at the intersection of Arthur Godfrey Road/West 41 Street and Jefferson Avenue

LANE CLOSURE INFORMATION
Travel lanes and sidewalks shall be closed only during non-peak hours on non-event days. Non-peak hours are:

  • 8 p.m. to 6 a.m., weekdays and weekends
Project At-A-Glance
 
map
Start Date
June 2021

Est. Completion
Early 2023

Construction Cost
$402,282

Lengths and Limits
From Alton Road to Meridian Avenue

FDOT North Miami-Dade Resident Engineer
Ivan Hay, P.E.

FDOT Project Manager
Igor Caicdeo

FDOT Project Administrator
Marina Gershanovich

Contractor
AUM Construction, Inc.

Community Outreach Specialist
Christian Gonzalez
O: (305) 640-7441
C: (786) 837-4884
ChristianS.Gonzalez@dot.state.fl.us
×