D6 Construction Logo

Home > Monroe County > US 1 18 mile stretch

 

US 1 (SR 5) The “18 Mile Stretch”

FIN No. 249635-1-52-01
WPI No. 249635

 

SR933 Road SignProject Limits

MP 0.362 to MP 4.15 in Miami-Dade County

 

Project Summary

This project includes complete reconstruction of US 1 to provide one travel lane in each direction divided by a concrete barrier wall; inside and outside shoulders including a northbound shoulder that can be used as an additional travel lane in the event of evacuation; as well as numerous environmental and hydrological enhancements including six box culverts for wildlife crossings.

 

Start Date: September 2006

 

Completion: Fall 2008

 

Construction Cost: $41 million

 

Project Team:

FDOT Construction Project Manager

Dari Vorce

 

Construction Engineer and Inspection

Parsons Brinkerhoff Construction Services

 

Contractor

Community Asphalt

 

Public Information

(305) 481-1186
PBUS1@bellsouth.net