Home > Monroe County > US 1 18 mile stretch
US 1 (SR 5) The “18 Mile Stretch”
FIN No. 249635-1-52-01
WPI No. 249635
Project Limits
MP 0.362 to MP 4.15 in Miami-Dade County
Project Summary
This project includes complete reconstruction of US 1 to provide one travel lane in each direction divided by a concrete barrier wall; inside and outside shoulders including a northbound shoulder that can be used as an additional travel lane in the event of evacuation; as well as numerous environmental and hydrological enhancements including six box culverts for wildlife crossings.
Start Date: September 2006
Completion: Fall 2008
Construction Cost: $41 million
Project Team:
FDOT Construction Project Manager
Dari Vorce
Construction Engineer and Inspection
Parsons Brinkerhoff Construction Services
Contractor
Community Asphalt
Public Information
(305) 481-1186
PBUS1@bellsouth.net