Tamiami Trail (SR 90) Safety Improvement Project
FIN No. 419658-1-52-01
WPI No. 419658
Project Limits
From 10 miles east of the Collier County Line (Mile Post 10) to a point east of Structure S-12E (Mile Post 13.8)
Project Summary
This project includes: shoulder milling and resurfacing, installing audible and vibratory pavement markings, as well as, a high-tension barrier fence and guardrail.
Start Date: September 29, 2008
Completion: Spring 2009
Construction Cost: Approximately $2.1 million
Project Team:
FDOT North Miami-Dade Resident Engineer
Ivan Hay, P.E.
Construction Engineering & Inspection
Bolton, Perez & Associates, Inc.
Contractor
Community Asphalt Corporation
Public Information Specialist
Jeannette Lazo
(305) 499-2417