Home > South Miami Dade > Tamiami Trail (SR 90) Safety Improvement Project

 

Tamiami Trail (SR 90) Safety Improvement Project

FIN No. 419658-1-52-01
WPI No. 419658

 

Project Limits

From 10 miles east of the Collier County Line (Mile Post 10) to a point east of Structure S-12E (Mile Post 13.8)

 

Project Summary

This project includes: shoulder milling and resurfacing, installing audible and vibratory pavement markings, as well as, a high-tension barrier fence and guardrail.

 

Start Date: September 29, 2008

 

Completion: Spring 2009

 

Construction Cost: Approximately $2.1 million

 

Project Team:

FDOT North Miami-Dade Resident Engineer

Ivan Hay, P.E.


Construction Engineering & Inspection

Bolton, Perez & Associates, Inc.

 

Contractor

Community Asphalt Corporation

 

Public Information Specialist

Jeannette Lazo
(305) 499-2417