D6 Construction Logo

Home > South Miami Dade > SW/NW 8th Avenue / US 441 (SR 7) Roadway Improvement Project

 

SW/NW 8th Avenue / US 441 (SR 7) Roadway Improvement Project

FIN No.416419-1-52-0101
WPI No. N/A

 

Project Limits

SE 8th Street – NE 3rd Street

 

Project Summary

The intent of the project is to enhance the area by: reconstructing sidewalks and driveways and upgrading curb ramps at various locations to meet Americans with Disabilities Act (ADA) standards; replacing curb and gutter at several locations; installing new pedestrian detectors. Once completed, this work will improve safety throughout the corridor for motorists and pedestrians.

 

 

Start Date: September 2008

 

Completion: Fall 2009

 

Construction Cost: $223,000

 

Project Team:

 

FDOT North Miami-Dade Resident Engineer:

Ivan Hay, P.E.

 

FDOT Project Engineer:

Sunday Enogieru, P.E.


Contractor

Horizon Contractors, Inc.

 

Public Information

Monica Diaz

305.499.2410

Monica.Diaz@dot.state.fl.us