SW 112th Street / Killian Drive (SR 990) Safety Improvement Project
FIN No.422703-1-52-01
WPI No. N/A
Project Limits
SW 112th Street / Killian Drive and SW 82nd Avenue
Project Summary
This project includes installing new traffic signals and signs; upgrading sidewalk and connecting curb ramps on the west side of SW 82nd Avenue only, to meet Americans with Disabilities Act (ADA) standards; installing new pedestrian signals; and re-striping the roadway. Once completed, this work will enhance traffic flow and safety through this intersection.
Start Date: August 2008
Completion: Fall 2008
Construction Cost: $267,000
Project Team:
FDOT North Miami-Dade Resident Engineer:
Ivan Hay, P.E.
Construction Engineering & Inspection:
Bolton, Perez & Associates
Contractor
Horsepower Electric
Public Information
Monica Diaz
305.499.2410