Home > South Miami Dade > Palmetto Expressway Expansion Project (SR 826)
Palmetto Expressway Expansion Project (SR 826)
FIN No. 249035-1-52-01
WPI No. 249035
Project Limits
Just north of SW 40th Street / Bird Road to just north of SW 72nd Street / Sunset Drive, including the SR 874 Interchange
Project Summary
This Design/Build Project includes widening SR 826 to include one new travel lane in each direction; reconstructing on and off ramps at the Bird Road, Miller Drive and SR 874 Interchanges and numerous roadway enhancements including: new storm water drainage; new roadway lighting and signage; new water mains (installed in coordination with Miami-Dade Water and Sewer Department) noise walls north of Bird Road and extensive landscaping.
Start Date: November 2008
Completion: Summer 2012
Construction Cost: $177 million
Project Team:
FDOT South Miami-Dade Resident Engineer
Mario Cabrera, P.E.
FDOT Construction Project Manager
Dari Vorce
FDOT Design Project Manager
Jason Chang, P.E.
Construction Engineering & Inspection
New Millennium Engineering
Contractor
The de Moya Group, Inc.
Public Information Specialist
Jeannette Lazo
(305) 499-2417
Jeannette.Lazo@dot.state.fl.us