D6 Construction Logo

Home > North Miami Dade > Biscayne Boulevard (SR 5) Landscaping Project 2

 

Biscayne Boulevard (SR 5) Landscaping Project

FIN No.250224-2-52-01
WPI No. 250224

 

SR933 Road SignProject Limits

NE 37th – NE 67th Street

 

Project Summary

The project includes a variety of landscape and decorative treatments to be installed in the median and along both sides of the corridor.  This is one of several related projects along Biscayne Boulevard designed to enhance the area and preserve the quality of the community.

 

Start Date: May 2008

 

Completion: December 2008

 

Construction Cost: $1.5 Million

 

Project Team:

FDOT North Miami-Dade Resident Engineer

Ivan Hay, P.E.

 

FDOT Project Manager

Amanda Shotton, P.E.

 

Construction Engineering & Inspection

Tamayo Engineering

 

Contractor

Vila and Sons Landscaping Corporation

 

Public Information

Monica Diaz
(305) 499-2410 or (305) 345-7269
monica.diaz@dot.state.fl.us