Home > North Miami Dade > Sunny Isles Boulevard (SR 826) Control House & Bridge Rehabilitation Project
Sunny Isles Boulevard (SR 826) Control House & Bridge Rehabilitation Project
FIN No. 250065-2-52-01
WPI No. N/A
Project Limits
Sunny Isles Boulevard Bascule Bridge over the Intracoastal Waterway.
Project Summary
Work includes structurally reinforcing the existing control house and refurbishing the lightning protection system, new windows, a closed circuit television system, and repairing the existing fender system.
Start Date: September 2008
Completion: Spring 2009
Construction Cost: $788, 000
Project Team:
FDOT North Miami-Dade Resident Engineer
Ivan Hay, P.E.
Construction Engineering & Inspection
Bolton, Perez & Associates, Inc.
Contractor
PCL Civil Constructors, Inc.
Public Information
Monica Diaz
305.499.2410
Monica.Diaz@dot.state.fl.us