NW 12th Avenue (SR 933) Bascule Bridge Replacement Project
FIN No. 249640-1-52-01
WPI No. 249640
Project Limits
NW 7th Street to NW 16th Street
Project Summary
The project centers on building two new three-lane, double leaf bascule (draw) bridges to replace the existing four-lane structure, which was built in the early 1900s. Improvements include:Road Reconstruction from NW 7th Street to NW 12th Street; Milling and resurfacing from NW 12th Street to NW 16th Street; new streetlights, traffic signals, and sidewalks; and aesthetic and architectural improvements.
Start Date: September 18, 2006
Completion: Late 2009
Construction Cost: $64 million
Project Team:
FDOT Project Manager
Hector A. Rodriguez
Construction Engineering & Inspection
Bermello Ajamil Construction Services, Inc.
Contractor
Kiewit Southern Corporation
Public Information
Tish Burgher
(305) 499-2391 or (305) 216-3617