Home > North Miami Dade >SR 836 / I-395 Bridge Rehabilitation Project
SR 836 / I-395 Bridge Rehabilitation Project
FIN No.422694-1-52-01
WPI No. 422694
Project Limits
Biscayne Boulevard west to I-95 (SR 9A)
Project Summary
This project is designed to strengthen and enhance these structures by rehabilitating columns and piers underneath the bridges and refurbishing concrete barrier walls and bridge joints on the roadway. .
Start Date: September 2008
Completion: Summer 2009
Construction Cost: $2.2 million
Project Team:
FDOT North Miami-Dade Resident Engineer
Ivan Hay, P.E.
FDOT Project Manager
Amanda Shotton, P.E.
Construction Engineering & Inspection
Carnahan Proctor & Cross / Tamayo Engineering
Contractor
J. Slagter Construction
Public Information
Monica Diaz
(305) 499-2410