Palmetto Expressway Intelligent Transportation System
(SR 826)
FIN No. 251686-1-52-01
WPI No. 251686
Project Limits
Along the Palmetto Expressway (SR 826) from NW 25th Street to I-75.
Project Summary
This Design/Build Project includes the installation and deployment of ITS-related devices including a Microwave Vehicle Detector System; Closed Circuit Television; Dynamic Message Signs; and a Fiber Optic Communications network.
Start Date: Fall 2008
Completion: Summer 2009
Construction Cost: $4.1 million
Project Team:
FDOT South Miami-Dade Resident Engineer
Mario Cabrera, P.E.
FDOT Construction Project Manager
Dari Vorce
FDOT Design Project Manager
Ali Toghiani
Construction Engineering & Inspection
DMJM Harris
Contractor
Trans Tech Electric, L.P.
Public Information
Jeannette Lazo
(305) 499-2417