Plantation Key from MM 85.7 to MM 86.8

 

Project Summary

The work to be performed consists of adding a new center merge lane for improved traffic operations and widening the shoulders to provide a bicycle path on both sides of the roadway. The project also will also provide new facilities for storm water drainage.

 

Start Date: Fall 2008


Completion:
Summer 2009

 

Construction Cost: $2.5 million

 

Project Team:

FDOT Project Manager

Charlie Phinizy, P.E.

 

CEI Project Engineer

Metric Engineering

 

Contractor

General Asphalt Company, Inc.

 

Public Information

Ashley Hoover

(305) 797-0962 (in Monroe County)