PROJECT SUMMARY

The Florida Department of Transportation (FDOT) has begun a roadway and lighting project along SR 994/Quail Roost Drive/SW 186 Street/SW 200 Street from west of SW 127 Avenue to SR 5/US 1/S Dixie Highway, in Miami-Dade County. 

WORK TO BE PERFORMED

  • Repaving the roadway along the project limits
  • Restoring and upgrading signs and pavement markings
  • Upgrading existing vehicular and pedestrian signals
  • Reconstructing ramps at existing pedestrian crosswalks
  • Reconstructing damaged driveways and sidewalks throughout the project limits 
  • Upgrading and/or adding light poles with new Light Emitting Diode (LED) fixture at signalized intersections with pedestrian crossings to increase brightness
  • Removing and/or replacing existing light poles at select locations 
  • Adding speed warning signs along Quail Roost Drive on the eastbound direction, at SW 125 Avenue; and on the westbound direction, at SW 194 Terrace
  • Improving drainage at select locations
  • Relocating wood fence at Quail Roost Park
  • Adding raised median islands with landscape between SW 194 Terrace and SW 193 Street and SW 190 Terrace
  • Replacing bridge railing over the canal 
  • Adjusting the utility manhole and valve covers in the areas of pavement restoration or sidewalk reconstruction

Lane closures shall occur only during non-peak hours on non-event days/nights/weekends. Non-peak hours are:

  • 9 a.m. to 3:30 p.m - weekdays and weekends
  • 9 p.m. to 5:30 a.m. - Sunday through Thursday nights
  • 11 p.m. to 7 a.m. - Friday and Saturday nights

Temporary sidewalk closures and pedestrian detours during non-peak hours will have minimal effects on traffic. 

Project At-A-Glance
 
map
Start Date
September 2021

Est. Completion
Summer 2022

Construction Cost
$4.1 million

Lengths and Limits
SR 994/Quail Roost Drive/SW 186 Street/SW 200 Street from west of SW 127 Avenue to SR 5/US1/S Dixie Highway

FDOT South Miami-Dade & Monroe Resident Engineer
Andres Berisiartu, P.E.

FDOT Project Manager
Jonathan Fundora, P.E.

FDOT Project Administrator
Jean Boursiquot

Contractor
Halley Engineering Contractors, Inc.

Public Information
Jeanette Gorgas
Media Relations Group, Inc.

O: (305) 254-8598

C: (786) 239-8862

Jgorgas@mrgmiami.com

×