PROJECT COMPLETED ON JANUARY 15, 2021

The Florida Department of Transportation (FDOT) completed construction of a roadway improvement project along SR 997/Krome Avenue from SW 312 Street to SW 232 Street in Miami-Dade County. 

WORK TO BE PERFORMED

SR 997/Krome Avenue from SW 296 Street to SW 232 Street:

  • Rebuilding and widening Krome Avenue from a two-lane roadway to a four-lane roadway divided by a grassed median
  • Installing a drainage system and two new bridges
  • Providing lighting along the length of the project
  • Installing guardrail in the median
  • Providing access management and improving traffic operations throughout the corridor
  • Installing a new signalized intersection at SW 272 Street

Along SR 997/Krome Avenue from SW 312 Street/Campbell Drive to SW 296 Street:

  • Repaving and restriping the roadway
  • Removing parking and bicycle lanes
  • Widening the roadway from SW 300 Street (NE 19 Street) to SW 296 Street to continue through lane
  • Improving drainage system
  • Enhancing existing traffic and pedestrian signals to current standards
  • Upgrading signage and pavement markings

LANE CLOSURE AND DETOUR INFORMATION

To do this work safely, one half of the road will be under construction at a time. Access to properties will be maintained unless coordinated in advance. Work and lane closures will occur during non-peak hours on non-event days, nights and weekends from:

  • 9 a.m. to 3:30 p.m., weekdays and weekends
  • 9 p.m. to 5:30 a.m., Sunday through Thursday
  • 11 p.m. to 7 a.m., Friday and Saturday

PROJECT UPDATE VIDEO

MARCH 2020 PROJECT UPDATE VIDEO

 

AUGUST 2020 PROJECT UPDATE VIDEO

KROME AVENUE TRAFFIC SHIFT ON FRIDAY, SEPTEMBER 11, 2020 VIDEO

Project At-A-Glance
 
map
Start Date
January 2020

Est. Completion
Early 2021

Construction Cost
$32.7 million

Lengths and Limits
State Road (SR) 997/Krome Avenue from SW 232 Street to SW 312 Street

FDOT South Miami-Dade Resident Engineer
Andres Berisiartu, P.E.

FDOT Construction Project Manager
Jonathan Fundora, P.E.

Construction Consulting Engineering and Inspection (CCEI) Senior Project Engineer
Felipe Gonzalez, P.E.
RK&K

Contractor
Halley Engineering Contractors, Inc.

Community Outreach Specialist
Heather M. Leslie

HML Public Outreach
Heather@HMLPublicOutreach.com
(305) 905-5876

×