South Florida Roads (Miami-Dade and Monroe Counties)
error icon
Sample text Sample text

EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

State of Florida Department of Transportation logo - link to the FDOT website
Florida Department of

TRANSPORTATION

South Florida Roads (Miami-Dade and Monroe Counties)

 
Welcome
 

The Florida Department of Transportation (FDOT) along with the Miami-Dade Expressway Authority (MDX) have started work on the $802 million I-395/SR 836/I-95 Design-Build Project. This project will be constructed concurrently by the Archer Western-de Moya Group Joint Venture to minimize impacts to the public. To view additional information please visit the project webpage at www.i395-miami.com.

WORK TO BE PERFORMED:

I-395 Reconstruction
  • Complete reconstruction of I-395 including a new signature bridge that will span over NE 2 Avenue and SR5/Biscayne Boulevard.
SR 836 Enhancements
  • Enhancements include double-decking SR 836 to provide drivers with a direct connection to the MacArthur Causeway that is free of local entry and exit traffic.
I-95 Concrete Pavement Reconstruction
  • Replacement of concrete pavement on both northbound and southbound travel lanes.

LANE CLOSURE INFORMATION:

To do this work safely, it will be necessary to perform traffic shifts and close travel lanes at times. Special events will be considered when scheduling closures. The noted hours below are for single lane closures, multi-lane closures will occur later. This contract allows for weekend closures on certain ramps. 

I-395 Reconstruction
  • 10 p.m. to 5:30 a.m., Sunday through Thursday nights
SR 836 Enhancements
  • 8 p.m. to 5:30 a.m., Sunday through Thursday nights
  • 8:30 p.m. to 9 a.m., Friday nights
  • 8:30 p.m. to 11 a.m., Saturday nights
I-95 Concrete Pavement Reconstruction
  • 9 p.m. to 5:30 a.m., Sunday through Thursday nights
RAMPS
  • 10 p.m. to 6:30 a.m., Sunday through Thursday nights
  • 11 p.m. to 7 a.m. Friday and Saturday nights
Project At-A-Glance
 
map
Start Date
October 2018

Est. Completion date
October 2023

Construction Cost
$802 million

Lengths and Limits
State Road (SR) 836 beginning at NW 17 Avenue and continuing through the SR 836/I-395/I-95 (Midtown) Interchange to the MacArthur Causeway. The limits on I-95 are from NW 8 Street to NW 29 Street.

FDOT Design Project Manager
Maria I. Perdomo, P.E.

FDOT Construction Project Manager
Jacqueline Sequeira, P.E.

Contractor
Archer Western – de Moya Joint Venture

Community Outreach Specialist
Oscar Gonzalez

(786) 280-0983
ogonzalez@mrgmiami.com