The Florida Department of Transportation (FDOT) along with the Greater Miami Expressway (GMX) is constructing the $840 million I-395/SR 836/I-95 Design-Build Project. These projects will be constructed concurrently by the Archer Western-de Moya Group Joint Venture to minimize impacts to the public. To view additional information please visit the project webpage at www.i395-miami.com.

WORK TO BE PERFORMED:

I-395 Reconstruction
  • Complete reconstruction of I-395 including a new signature bridge that will span over NE 2 Avenue and SR5/Biscayne Boulevard.
SR 836 Enhancements
  • Enhancements include double-decking SR 836 to provide drivers with a direct connection to the MacArthur Causeway that is free of local entry and exit traffic.
I-95 Concrete Pavement Reconstruction
  • Replacement of concrete pavement on both northbound and southbound travel lanes.

LANE CLOSURE INFORMATION:

To do this work safely, it will be necessary to shift traffic, close lanes and detour traffic at times. Special events will be considered when scheduling closures. The noted hours below are for single lane closures, multi-lane closures will occur later. This contract allows for weekend closures and detours. 

I-395 Reconstruction
  • 10 p.m. to 5:30 a.m., Sunday through Thursday nights
SR 836 Enhancements
  • 8 p.m. to 5:30 a.m., Sunday through Thursday nights
  • 8:30 p.m. to 9 a.m., Friday nights
  • 8:30 p.m. to 11 a.m., Saturday nights
I-95 Concrete Pavement Reconstruction
  • 9 p.m. to 5:30 a.m., Sunday through Thursday nights
RAMPS
  • 10 p.m. to 6:30 a.m., Sunday through Thursday nights
  • 11 p.m. to 7 a.m. Friday and Saturday nights
Project At-A-Glance
 
map
Start Date
April 2019

Est. Completion
Late 2027

Construction Cost
$840 million

Lengths and Limits
State Road (SR) 836 beginning at NW 17 Avenue and continuing through the SR 836/I-395/I-95 (Midtown) Interchange to the MacArthur Causeway. The limits on I-95 are from NW 8 Street to NW 29 Street.

FDOT Design Project Manager
Auraliz Benitez, P.E.

FDOT Construction Project Manager
Jacqueline Sequeira, P.E.

Contractor
Archer Western – de Moya Joint Venture

Community Outreach Specialist
Oscar Gonzalez

(786) 280-0983
oscar.gonzalez2@dot.state.fl.us